Live calculation engineNo Database Required

Residential — Alterations & Additions

9 Sample Street, Caulfield South VIC

View Full QS Report
Commercial Modifiers & SpecificationsStep 2

Pricing Modifiers, Systems & Escalation Index

Builder's Margin

15.0%

Applied as a direct commercial multiplier across trade subtotal before GST. Represents overhead, supervision, site administration, and target profit.

5%15% (Typical)25%35%
Margin Impact:$177,348 ex GST

Design & Construction Contingency

7.0%

Allowance for unknown site conditions, documentation gaps, and unforeseen variations during execution.

0%7% (Standard)15%25%
Contingency Impact:$82,762 ex GST
Australian Goods & Services Tax (GST) is calculated at exactly 10.0% over Total Ex-GST.
10% Statutory GST
Projected Financial Impact
Delta vs Previous:+$0 (0.0%)

Trade Sub-total

$1,182,317

Margin 15%

$177,348

Contingency 7%

$82,762

Total Ex-GST

$1,442,427

Total Inc-GST

$1,586,670

Rate $/m²

$6,442

Sub-total

$1,182,317

Margin 15.0%

$177,348

Contingency 7.0%

$82,762

Total ex GST

$1,442,427

Inc GST

$1,586,670

Cost per m²

$6,442

6 conditions changed this estimate

Two or more storeys require a full perimeter scaffold

At two storeys and above the work platform exceeds 4m, which mandates a licensed scaffold with a working deck per level rather than trestles. Scaffold face area is perimeter × wall height × storeys, so a double-storey job carries roughly double the scaffold area of a single-storey job of the same footprint, plus a longer hire period.

Two or more storeys require suspended floor structure and a stair

Suspended floor framing, floor insulation and a stair only exist above one storey. Two-storey construction adds 15–20% to the base rate per m², covering these plus the additional steel and more complex structural engineering.

Precast, portal frame and truss erection require a crane

Panel and portal erection cannot proceed without lifting plant.

Renovation requires protection of retained structure and finishes

Work adjacent to occupied or retained fabric carries protection, propping and make-good costs that do not exist on a greenfield build. Make-good is the line item most often missed in renovation estimates.

Pre-1990 buildings require a hazardous materials survey

Asbestos and lead paint must be identified before demolition on any building that predates 1990. The survey is priced; removal is normally excluded and carried as a provisional sum because the extent is unknowable until the survey is done.

Lightweight wall systems allow a reduced footing design

A wall system under half the dead load of brick veneer can permit a lighter slab and footing design on reactive clay. On Melbourne Class H sites this saving frequently exceeds the panel premium — worth checking against the structural engineer before assuming the brick footing design.

Bill of Quantities

181 lines · 24 trades · vic-metro/2026-Q3

166 lines (92% of trade cost) are priced from unverified rates.

Review those rates before this estimate is issued to anyone outside the practice.

DescriptionQtyUnitRateTotal
Scaffolding — Erect, Dismantle & Certify238m2$35$8,316
Crane Hire — Truss & Steel Erection2ea$3,200$6,400
Scaffolding Hire — Ongoing15wks$350$5,268
Site Fencing1item$1,200$1,200
Signage1item$1,000$1,000
Skip Bins35ea$880$30,786
Toilet hire35wks$135$4,725
Extinguisher1item$300$300
First Aid1item$300$300
Temporary Power1item$1,200$1,200
Construction Insurance6month$1,350$8,100
Management Software6month$500$3,000
Petty Cash1item$5,000$5,000
Protective Equipment1item$1,000$1,000
Surveyors Set-Out2item$3,500$7,000
Final Clean1item$3,500$3,500
Window Cleaning (internal + external)1item$1,200$1,200
WHS Plan, SWMS & Site Induction1item$1,450$1,450
Site Container, Tool Shed & Office1item$4,500$4,500
Temporary Water & Backflow Prevention1item$950$950
Crossover & Kerb Protection1item$1,800$1,800
Site Access Road — Crushed Rock1item$4,800$4,800
Domestic Building Insurance (Home Warranty)224m2$1$224
Building Surveyor Inspections1item$2,800$2,800
Handover Documentation & Certificates1item$1,650$1,650
Protection — Films, Goop & Floor Protection224m2$12$2,687
Temporary Stair Protection1item$450$450
Sub-total
$1,182,317
Builder's margin @ 15%
$177,348
Contingency @ 7%
$82,762
Total ex GST
$1,442,427
Inc GST
$1,586,670