Residential — Alterations & Additions (Caulfield South)
Caulfield South VIC, Caulfield South VIC 3162 · LGA: Glen Eira
VALUATION BASE
melbourne-metro · vic-metro/2026-Q3
Report Date: 06 Aug 2026
Building Type
Residential — Alterations & Additions
Gross Floor Area
224 m²
Storeys
2
Trades Measured
24
Priced Line Items
181
Total Ex GST
$1,442,427
Executive Cost Summary
SECTION 1| Item / Cost Stage | Amount (AUD) |
|---|---|
| Net Subcontractor & Trade Cost | $1,182,317 |
| Builder’s Margin & Overhead | $177,348 |
| Design & Estimating Contingency | $82,762 |
| TOTAL ESTIMATED COST (EX GST) | $1,442,427 |
| Goods & Services Tax (GST) | $144,243 |
| TOTAL ESTIMATED COST (INC GST) | $1,586,670 |
Gemini AI QS Advisor & Scope Auditor
Powered by Google Gemini 3.6 Flash · Instant Australian construction intelligence & value engineering
Market Cost $/m² Validation
Project Rate (Ex GST)
$6,442/m²
Based on 223.9 m² GFA
Observed Market Band
$1,455 – $5,909
Typical: $2,364/m² (VIC)
Trade Subcontractor Rate
$5,281/m²
Excludes builder margin & contingency
Building Classification
residential_alts
MELBOURNE METRO
Sanity Observations & Variance Flags
Elemental Trade Cost Breakdown
Subcontractor baseline vs Standard QS distributionCondition Triggers & Project Specifics (6)
Two or more storeys require a full perimeter scaffold
At two storeys and above the work platform exceeds 4m, which mandates a licensed scaffold with a working deck per level rather than trestles. Scaffold face area is perimeter × wall height × storeys, so a double-storey job carries roughly double the scaffold area of a single-storey job of the same footprint, plus a longer hire period.
Two or more storeys require suspended floor structure and a stair
Suspended floor framing, floor insulation and a stair only exist above one storey. Two-storey construction adds 15–20% to the base rate per m², covering these plus the additional steel and more complex structural engineering.
Precast, portal frame and truss erection require a crane
Panel and portal erection cannot proceed without lifting plant.
Renovation requires protection of retained structure and finishes
Work adjacent to occupied or retained fabric carries protection, propping and make-good costs that do not exist on a greenfield build. Make-good is the line item most often missed in renovation estimates.
Pre-1990 buildings require a hazardous materials survey
Asbestos and lead paint must be identified before demolition on any building that predates 1990. The survey is priced; removal is normally excluded and carried as a provisional sum because the extent is unknowable until the survey is done.
Lightweight wall systems allow a reduced footing design
A wall system under half the dead load of brick veneer can permit a lighter slab and footing design on reactive clay. On Melbourne Class H sites this saving frequently exceeds the panel premium — worth checking against the structural engineer before assuming the brick footing design.
Trade Breakdown & Elemental Distribution
SECTION 2Elemental Cost Groups (Share of Trade Cost)
| # | Trade Section | Items | Section Total (AUD) | % Trade Cost | Cost / m² GFA |
|---|---|---|---|---|---|
| 01 | PRELIMINARIES | 27 | $109,606 | 9.3% | $490 |
| 02 | DEMOLITION | 8 | $63,367 | 5.4% | $283 |
| 03 | GROUND WORK & EXCAVATION | 7 | $17,537 | 1.5% | $78 |
| 04 | CONCRETING | 7 | $18,039 | 1.5% | $81 |
| 05 | STRUCTURAL STEEL | 1 | $20,000 | 1.7% | $89 |
| 06 | BRICKWORK | 4 | $29,501 | 2.5% | $132 |
| 07 | METALWORK | 2 | $7,322 | 0.6% | $33 |
| 08 | CARPENTRY | 15 | $163,509 | 13.8% | $730 |
| 09 | GLAZING | 5 | $45,032 | 3.8% | $201 |
| 10 | INSULATION | 4 | $11,828 | 1.0% | $53 |
| 11 | ROOFING & ROOF PLUMBING | 8 | $62,767 | 5.3% | $280 |
| 12 | DOORS | 6 | $16,475 | 1.4% | $74 |
| 13 | PLASTERBOARD | 3 | $49,173 | 4.2% | $220 |
| 14 | FLOOR & WALL FINISHES | 12 | $66,070 | 5.6% | $295 |
| 15 | WATERPROOFING | 9 | $22,454 | 1.9% | $100 |
| 16 | RENDER | 1 | $3,109 | 0.3% | $14 |
| 17 | PAINTING | 6 | $25,844 | 2.2% | $115 |
| 18 | HYDRAULICS | 9 | $38,575 | 3.3% | $172 |
| 19 | ELECTRICAL | 6 | $24,620 | 2.1% | $110 |
| 20 | MECHANICAL | 2 | $22,750 | 1.9% | $102 |
| 21 | LANDSCAPING | 3 | $12,597 | 1.1% | $56 |
| 22 | JOINERY | 12 | $53,476 | 4.5% | $239 |
| 23 | FIXTURES & FITTING | 22 | $57,166 | 4.8% | $255 |
| 24 | LABOUR & SITE MANAGEMENT | 2 | $241,500 | 20.4% | $1,079 |
| TOTAL MEASURED TRADES | 181 items | $1,182,317 | 100.0% | $5,281 | |
Stage Plan & Progress Claim Milestones
Work Breakdown Structure (WBS) aligned with standard Australian HIA / MBA construction contracts.
| Stage | Name & Scope | Engaged Trades | Duration Share | Progress Claim | Estimated Value (Ex GST) |
|---|---|---|---|---|---|
| RA-00 | Investigation & Hazardous Materials Pre-works dilapidation survey, hazardous materials (asbestos, lead paint) survey, service location, structural investigation of what is being retained. | HAZCER | 3% | — | $43,273 |
| RA-01 | Preliminaries & Protection Site establishment plus the protection work unique to renovation: dust screens, floor and façade protection, propping of retained structure, weather protection to open areas. | PRESUPSCF | 5% | — | $72,121 |
| RA-02 | Disconnection & Demolition Service disconnection, soft strip, structural demolition, waste segregation and removal, temporary make-safe of exposed edges. | DEMHAZHYDELE | 8% | — | $115,394 |
| RA-03 | Underpinning & New Substructure Underpinning or needle-propping where new loads bear on existing footings, new footings and slab to the addition, tie-in to existing. | EXCPILCONTER | 8% | — | $115,394 |
| RA-04 | Structural Frame & Tie-in New framing, steel beams to replace removed load-bearing walls, upper floor framing, roof framing and the junction detail back to the existing roof. | CARSTLCRNSCF | 11% | — | $158,667 |
| RA-05 | Roof & Weatherproofing New roof cover, re-roofing of the retained portion where in scope, flashings at the new/existing junction, gutters and downpipes. | ROFINSWPF | 7% | — | $100,970 |
| RA-06 | External Walls & Lock-up External wall system to the addition, re-cladding of the existing where in scope, windows and external doors, junction sealing. | BWKCLDGLZDORSCF | 10% | — | $144,243 |
| RA-07 | Services Rough-in & Existing Upgrade Rough-in to new areas, plus the upgrade and re-routing of existing services the new work triggers — switchboard capacity, drainage falls, hot water sizing. | HYDELEGASMECDAT | 7% | — | $100,970 |
| RA-08 | Insulation & Internal Linings Insulation, plasterboard, cornice, and patching where new work meets retained finishes. | INSPLB | 7% | — | $100,970 |
| RA-09 | Wet Area Preparation Wet area sheeting, screed, waterproof membrane and certification. | CARWPF | 4% | — | $57,697 |
| RA-10 | Fixing & Joinery Doors, skirting, architraves, stairs, kitchen, bathroom and wardrobe joinery — matched to existing profiles where the retained areas are visible. | CARDORJOI | 9% | — | $129,818 |
| RA-11 | Finishes & Make-good Tiling, render, painting, floor coverings. Make-good of retained areas disturbed by the works — the line item most often missed in renovation estimates. | TILRNDPNTFLR | 10% | — | $144,243 |
| RA-12 | Services Fit-off Tapware, sanitaryware, light fittings, switches, appliances, heating and cooling. | HYDELEMECFIX | 4% | — | $57,697 |
| RA-13 | External Works & Reinstatement Decking, paving, fencing and landscaping, including reinstatement of areas damaged by site access. | PAVDCKFENLND | 4% | — | $57,697 |
| RA-14 | Completion & Handover Defect rectification, final clean including the retained areas, compliance certificates, occupancy permit where required. | CLNCERSUP | 3% | Practical Completion | $43,273 |
Itemized Bill of Quantities
Full measurement schedule with Victorian market unit rates and mathematical formulas.
| Trade | Description & Reference | Qty | Unit | Rate | Total (AUD) |
|---|---|---|---|---|---|
| 1. PRELIMINARIES | Scaffolding — Erect, Dismantle & CertifyID: pre.scaffolding | 238 | m2 | $35 | $8,316 |
| 1. PRELIMINARIES | Crane Hire — Truss & Steel ErectionID: pre.crane_hire | 2 | ea | $3,200 | $6,400 |
| 1. PRELIMINARIES | Scaffolding Hire — OngoingID: pre.scaffold_hire | 15 | wks | $350 | $5,268 |
| 1. PRELIMINARIES | Site FencingID: pre.site_fencing | 1 | item | $1,200 | $1,200 |
| 1. PRELIMINARIES | SignageID: pre.signage | 1 | item | $1,000 | $1,000 |
| 1. PRELIMINARIES | Skip BinsID: pre.skip_bins | 35 | ea | $880 | $30,786 |
| 1. PRELIMINARIES | Toilet hireID: pre.toilet_hire | 35 | wks | $135 | $4,725 |
| 1. PRELIMINARIES | ExtinguisherID: pre.extinguisher | 1 | item | $300 | $300 |
| 1. PRELIMINARIES | First AidID: pre.first_aid | 1 | item | $300 | $300 |
| 1. PRELIMINARIES | Temporary PowerID: pre.temp_power | 1 | item | $1,200 | $1,200 |
| 1. PRELIMINARIES | Construction InsuranceID: pre.insurance | 6 | month | $1,350 | $8,100 |
| 1. PRELIMINARIES | Management SoftwareID: pre.mgmt_software | 6 | month | $500 | $3,000 |
| 1. PRELIMINARIES | Petty CashID: pre.petty_cash | 1 | item | $5,000 | $5,000 |
| 1. PRELIMINARIES | Protective EquipmentID: pre.ppe | 1 | item | $1,000 | $1,000 |
| 1. PRELIMINARIES | Surveyors Set-OutID: pre.surveyor_setout | 2 | item | $3,500 | $7,000 |
| 1. PRELIMINARIES | Final CleanID: pre.final_clean | 1 | item | $3,500 | $3,500 |
| 1. PRELIMINARIES | Window Cleaning (internal + external)ID: pre.window_clean | 1 | item | $1,200 | $1,200 |
| 2. DEMOLITION | Demolition of Existing StructureID: dem.existing_structure | 224 | m2 | $165 | $36,944 |
| 2. DEMOLITION | Waste RemovalID: dem.waste_removal | 22 | ea | $700 | $15,673 |
| 2. DEMOLITION | Disconnection — WaterID: dem.disconnect_water | 1 | item | $650 | $650 |
| 2. DEMOLITION | Disconnection — ElectricalID: dem.disconnect_electrical | 1 | item | $650 | $650 |
| 2. DEMOLITION | Protection — Existing BuildingID: dem.protect_existing | 1 | item | $5,500 | $5,500 |
| 2. DEMOLITION | Protection — Windows / FaçadeID: dem.protect_facade | 1 | item | $1,500 | $1,500 |
| 2. DEMOLITION | Protection — InternalID: dem.protect_internal | 1 | item | $1,500 | $1,500 |
| 2. DEMOLITION | Hazardous Materials SurveyID: haz.survey | 1 | item | $950 | $950 |
| 3. GROUND WORK & EXCAVATION | Strip Footing ExcavationID: gnd.strip_footing_exc | 9 | m3 | $135 | $1,242 |
| 3. GROUND WORK & EXCAVATION | Ground Slab ExcavationID: gnd.slab_exc | 4 | m3 | $135 | $540 |
| 3. GROUND WORK & EXCAVATION | Removal & Tipping CostID: gnd.removal_tipping | 13 | m3 | $85 | $1,122 |
| 3. GROUND WORK & EXCAVATION | Perimeter Termite ProtectionID: gnd.termite_protection | 19 | lm | $35 | $665 |
| 3. GROUND WORK & EXCAVATION | Manual ExcavationID: gnd.manual_excavation | 160 | hours | $65 | $10,400 |
| 3. GROUND WORK & EXCAVATION | Termite Collars to Slab PenetrationsID: gnd.termite_collars | 14 | ea | $95 | $1,368 |
| 4. CONCRETING | Strip FootingID: con.strip_footing | 8 | m3 | $720 | $5,760 |
| 4. CONCRETING | Ground SlabID: con.ground_slab | 4 | m3 | $720 | $2,880 |
| 4. CONCRETING | Concrete StairID: con.stair | 1 | no | $6,500 | $6,500 |
| 4. CONCRETING | Concrete FinishID: con.finish | 15 | m2 | $5 | $75 |
| 4. CONCRETING | Damp Proof CourseID: con.dpc | 18 | m2 | $8 | $144 |
| 4. CONCRETING | Concrete PumpID: con.pump | 1 | ea | $2,500 | $2,500 |
| 5. STRUCTURAL STEEL | Structural Steel Allowance — Beams & PostsID: stl.allowance | 1 | item | $20,000 | $20,000 |
| 6. BRICKWORK | Masonry Wall — Secondary / RetainedID: bwk.secondary_masonry | 56 | m2 | $460 | $25,820 |
| 6. BRICKWORK | LintelsID: bwk.lintels | 30 | m | $85 | $2,550 |
| 6. BRICKWORK | Brick Ties & Cavity ClosersID: bwk.wall_ties | 56 | m2 | $12 | $674 |
| 6. BRICKWORK | Weep HolesID: bwk.weep_holes | 51 | lm | $9 | $457 |
| 7. METALWORK | HandrailID: mtl.handrail | 4 | m | $650 | $2,522 |
| 7. METALWORK | Privacy ScreensID: mtl.privacy_screen | 4 | m2 | $1,200 | $4,800 |
| 8. CARPENTRY | Frame Erection — PrefabricatedID: car.frame_install_prefab | 22 | sq | $400 | $8,956 |
| 8. CARPENTRY | External Wall FramingID: car.ext_frame | 131 | m2 | $150 | $19,650 |
| 8. CARPENTRY | Wall SarkingID: car.wall_sarking | 131 | m2 | $45 | $5,895 |
| 8. CARPENTRY | Internal Wall FramingID: car.int_frame | 140 | m2 | $150 | $21,036 |
| 8. CARPENTRY | First Floor Framing & BoardID: car.upper_floor | 105 | m2 | $210 | $22,052 |
| 8. CARPENTRY | Wet Area & Balcony CFC FlooringID: car.cfc_floor | 38 | m2 | $120 | $4,560 |
| 8. CARPENTRY | Roof FramingID: car.roof_frame | 130 | m2 | $165 | $21,450 |
| 8. CARPENTRY | External Wall CladdingID: car.ext_cladding | 131 | m2 | $170 | $22,270 |
| 8. CARPENTRY | SkirtingID: car.skirting | 94 | lm | $55 | $5,170 |
| 8. CARPENTRY | ArchitravesID: car.architrave | 206 | lm | $35 | $7,210 |
| 8. CARPENTRY | StairID: car.stair | 1 | ea | $15,000 | $15,000 |
| 8. CARPENTRY | Duct & Box-OutID: car.duct_boxout | 1 | item | $2,500 | $2,500 |
| 8. CARPENTRY | Fixings, Bracing, Tie-Downs & Structural ConnectorsID: car.fixings_bracing | 224 | m2 | $18 | $4,030 |
| 9. GLAZING | Glazed Doors & WindowsID: glz.doors_windows | 45 | m2 | $850 | $38,531 |
| 9. GLAZING | BalustradeID: glz.balustrade | 4 | m | $450 | $1,746 |
| 9. GLAZING | SkylightID: glz.skylight | 1 | m2 | $1,500 | $2,055 |
| 9. GLAZING | Sliding / Stacker Door — Premium Over Standard GlazingID: glz.sliding_uplift | 1 | ea | $900 | $900 |
| 9. GLAZING | Bifold Door — Premium Over Standard GlazingID: glz.bifold_uplift | 1 | ea | $1,800 | $1,800 |
| 10. INSULATION | Roof InsulationID: ins.roof | 130 | m2 | $36 | $4,680 |
| 10. INSULATION | First Floor InsulationID: ins.upper_floor | 105 | m2 | $36 | $3,780 |
| 10. INSULATION | External Wall Insulation — R2.5 BattsID: ins.external_wall | 131 | m2 | $18 | $2,358 |
| 10. INSULATION | Internal Acoustic Insulation — Wet Areas & BedroomsID: ins.internal_acoustic | 63 | m2 | $16 | $1,010 |
| 11. ROOFING & ROOF PLUMBING | Roof Cover — TilesID: rof.cover_tile | 66 | m2 | $165 | $10,903 |
| 11. ROOFING & ROOF PLUMBING | Roof Cover — MetalID: rof.cover_metal | 64 | m2 | $185 | $11,759 |
| 11. ROOFING & ROOF PLUMBING | Roof GutteringID: rof.guttering | 98 | lm | $85 | $8,330 |
| 11. ROOFING & ROOF PLUMBING | DownpipesID: rof.downpipes | 9 | ea | $320 | $2,880 |
| 11. ROOFING & ROOF PLUMBING | Roof BattensID: rof.battens | 130 | m2 | $35 | $4,550 |
| 11. ROOFING & ROOF PLUMBING | Roof SarkingID: rof.sarking | 130 | m2 | $28 | $3,640 |
| 11. ROOFING & ROOF PLUMBING | Roof FasciaID: rof.fascia | 101 | lm | $120 | $12,120 |
| 11. ROOFING & ROOF PLUMBING | Eaves LiningID: rof.eaves_lining | 101 | m2 | $85 | $8,585 |
| 12. DOORS | Internal Doors — Hollow Core 2040ID: dor.internal_hollow | 9 | no | $1,000 | $9,000 |
| 12. DOORS | Door StopsID: dor.stops | 9 | no | $25 | $225 |
| 12. DOORS | Door HardwareID: dor.hardware | 9 | no | $250 | $2,250 |
| 12. DOORS | Door Jambs & FramesID: dor.jambs | 13 | no | $180 | $2,340 |
| 12. DOORS | Weather & Draught SealsID: dor.weather_seals | 4 | no | $65 | $260 |
| 13. PLASTERBOARD | Wall PlasterboardID: plb.wall | 411 | m2 | $65 | $26,746 |
| 13. PLASTERBOARD | Ceiling PlasterboardID: plb.ceiling | 235 | m2 | $75 | $17,632 |
| 13. PLASTERBOARD | CorniceID: plb.cornice | 137 | lm | $35 | $4,795 |
| 14. FLOOR & WALL FINISHES | Wet Area Floor Tiling — InstallID: fin.floor_tile_install | 30 | m2 | $150 | $4,569 |
| 14. FLOOR & WALL FINISHES | Wet Area Wall Tiling — InstallID: fin.wall_tile_install | 133 | m2 | $150 | $20,016 |
| 14. FLOOR & WALL FINISHES | Floor Screeding to Tiling AreaID: fin.screed | 38 | m2 | $70 | $2,660 |
| 14. FLOOR & WALL FINISHES | Balcony FinishID: fin.balcony_finish | 7 | m2 | $100 | $730 |
| 14. FLOOR & WALL FINISHES | Balcony Skirting TileID: fin.balcony_skirting | 13 | lm | $50 | $647 |
| 14. FLOOR & WALL FINISHES | CaulkingID: fin.caulking | 5 | ea | $600 | $3,000 |
| 14. FLOOR & WALL FINISHES | Repair Existing Flooring (Ground)ID: fin.repair_existing | 1 | item | $5,500 | $5,500 |
| 14. FLOOR & WALL FINISHES | Shower Niche — Form, Waterproof & TileID: fin.shower_niche | 3 | ea | $650 | $1,950 |
| 14. FLOOR & WALL FINISHES | Tile Edge Trims & Corner BeadsID: fin.tile_trims | 60 | lm | $28 | $1,680 |
| 15. WATERPROOFING | Wet Area FloorID: wpf.wet_floor | 30 | m2 | $70 | $2,132 |
| 15. WATERPROOFING | Wet Area WallID: wpf.wet_wall | 133 | m2 | $70 | $9,341 |
| 15. WATERPROOFING | Balcony WaterproofingID: wpf.balcony | 7 | m2 | $85 | $621 |
| 15. WATERPROOFING | Sill & Head Flashing to OpeningsID: wpf.opening_flashing | 22 | ea | $85 | $1,870 |
| 15. WATERPROOFING | Cavity Tray & Base FlashingID: wpf.cavity_flashing | 51 | lm | $38 | $1,930 |
| 15. WATERPROOFING | Apron & Step Flashing — Roof to WallID: wpf.roof_wall_junction | 24 | lm | $95 | $2,280 |
| 15. WATERPROOFING | Penetration Flashing CollarsID: wpf.penetration | 6 | ea | $120 | $720 |
| 15. WATERPROOFING | External Sealant to Openings & JointsID: wpf.external_sealant | 110 | lm | $22 | $2,420 |
| 16. RENDER | Render to Brick WallID: rnd.brick_wall | 57 | m2 | $55 | $3,109 |
| 17. PAINTING | Wall PaintingID: pnt.wall | 411 | m2 | $25 | $10,287 |
| 17. PAINTING | Ceiling PaintingID: pnt.ceiling | 235 | m2 | $25 | $5,877 |
| 17. PAINTING | Render PaintingID: pnt.render | 57 | m2 | $35 | $1,995 |
| 17. PAINTING | External Cladding PaintingID: pnt.ext_cladding | 131 | m2 | $35 | $4,585 |
| 17. PAINTING | DoorsID: pnt.doors | 9 | ea | $250 | $2,250 |
| 18. HYDRAULICS | Hot & Cold Water PointsID: hyd.water_points | 30 | no | $530 | $15,900 |
| 18. HYDRAULICS | Sewage PointsID: hyd.sewer_points | 21 | no | $530 | $11,130 |
| 18. HYDRAULICS | Gas PointsID: hyd.gas_points | 2 | item | $1,200 | $2,400 |
| 18. HYDRAULICS | Tempering Valve — Install & CommissionID: hyd.tempering_valve | 1 | ea | $450 | $450 |
| 18. HYDRAULICS | Floor Waste & Puddle FlangeID: hyd.floor_waste | 5 | ea | $280 | $1,400 |
| 18. HYDRAULICS | Stormwater Drainage & ConnectionID: hyd.stormwater_connection | 1 | item | $4,500 | $4,500 |
| 19. ELECTRICAL | Light PointsID: ele.light_points | 37 | no | $320 | $11,840 |
| 19. ELECTRICAL | Power PointsID: ele.power_points | 25 | no | $320 | $8,000 |
| 19. ELECTRICAL | Data PointsID: ele.data_points | 1 | no | $320 | $320 |
| 19. ELECTRICAL | TV PointsID: ele.tv_points | 1 | no | $320 | $320 |
| 19. ELECTRICAL | Switchboard Upgrade & Safety SwitchesID: ele.switchboard_upgrade | 1 | item | $2,400 | $2,400 |
| 19. ELECTRICAL | Smoke Alarms — Hardwired & InterconnectedID: ele.smoke_alarms | 6 | ea | $290 | $1,740 |
| 20. MECHANICAL | Exhaust FanID: mec.exhaust_fan | 5 | ea | $550 | $2,750 |
| 20. MECHANICAL | Air Conditioning AllowanceID: mec.aircon_allowance | 1 | item | $20,000 | $20,000 |
| 21. LANDSCAPING | External DeckID: lnd.external_deck | 17 | m2 | $550 | $9,317 |
| 22. JOINERY | Bathroom JoineryID: joi.bathroom | 5 | m | $1,300 | $5,915 |
| 22. JOINERY | Bathroom BenchID: joi.bathroom_bench | 5 | m | $800 | $3,640 |
| 22. JOINERY | Bathroom Shaving CabinetID: joi.shaving_cabinet | 5 | m | $1,200 | $5,460 |
| 22. JOINERY | Kitchen JoineryID: joi.kitchen | 4 | m | $1,500 | $6,600 |
| 22. JOINERY | Kitchen Overhead JoineryID: joi.kitchen_overhead | 4 | m | $950 | $4,180 |
| 22. JOINERY | Pantry JoineryID: joi.pantry | 4 | m | $1,500 | $5,805 |
| 22. JOINERY | Kitchen BenchtopID: joi.kitchen_benchtop | 4 | m | $800 | $3,520 |
| 22. JOINERY | Kitchen SplashbackID: joi.kitchen_splashback | 4 | m | $380 | $1,672 |
| 22. JOINERY | Wardrobe JoineryID: joi.wardrobe | 7 | m | $1,000 | $6,590 |
| 22. JOINERY | Laundry JoineryID: joi.laundry | 4 | m | $1,500 | $6,105 |
| 22. JOINERY | Laundry BenchtopID: joi.laundry_benchtop | 4 | m | $600 | $2,442 |
| 22. JOINERY | Laundry SplashbackID: joi.laundry_splashback | 4 | m | $380 | $1,547 |
| 23. FIXTURES & FITTING | BasinID: fix.basin | 4 | no | $850 | $3,400 |
| 23. FIXTURES & FITTING | Basin MixerID: fix.basin_mixer | 4 | no | $450 | $1,800 |
| 23. FIXTURES & FITTING | BathsID: fix.bath | 2 | no | $800 | $1,600 |
| 23. FIXTURES & FITTING | Bath MixerID: fix.bath_mixer | 2 | no | $450 | $900 |
| 23. FIXTURES & FITTING | ToiletID: fix.toilet | 3 | no | $600 | $1,800 |
| 23. FIXTURES & FITTING | Shower ScreensID: fix.shower_screen | 3 | no | $2,350 | $7,050 |
| 23. FIXTURES & FITTING | Shower MixerID: fix.shower_mixer | 3 | no | $650 | $1,950 |
| 23. FIXTURES & FITTING | MirrorID: fix.mirror | 4 | no | $300 | $1,200 |
| 23. FIXTURES & FITTING | Towel RailID: fix.towel_rail | 3 | no | $350 | $1,050 |
| 23. FIXTURES & FITTING | Bathroom FittingsID: fix.bathroom_fittings | 3 | no | $300 | $900 |
| 23. FIXTURES & FITTING | Linear DrainsID: fix.linear_drain | 3 | m | $350 | $1,190 |
| 23. FIXTURES & FITTING | Drain WastesID: fix.drain_waste | 8 | no | $35 | $280 |
| 23. FIXTURES & FITTING | Kitchen AppliancesID: fix.kitchen_appliances | 1 | no | $10,000 | $10,000 |
| 23. FIXTURES & FITTING | Sink & TapID: fix.sink_tap | 2 | no | $2,500 | $5,000 |
| 23. FIXTURES & FITTING | Laundry Tap & TubID: fix.laundry_tap_tub | 1 | no | $2,500 | $2,500 |
| 23. FIXTURES & FITTING | Hot Water UnitID: fix.hot_water_unit | 1 | no | $1,000 | $1,000 |
| 23. FIXTURES & FITTING | Wet Area Floor TileID: fix.floor_tile_supply | 34 | m2 | $50 | $1,675 |
| 23. FIXTURES & FITTING | Wet Area Wall TileID: fix.wall_tile_supply | 147 | m2 | $50 | $7,339 |
| 23. FIXTURES & FITTING | Balcony TileID: fix.balcony_tile_supply | 8 | m2 | $50 | $402 |
| 23. FIXTURES & FITTING | Light FittingsID: fix.light_fittings | 37 | ea | $60 | $2,220 |
| 24. LABOUR & SITE MANAGEMENT | Labour / Carpenter — 50% allocationID: lab.carpenter | 18 | wks | $3,800 | $66,500 |
| 24. LABOUR & SITE MANAGEMENT | Site SupervisionID: lab.site_supervision | 35 | wks | $5,000 | $175,000 |
| 1. PRELIMINARIES | WHS Plan, SWMS & Site InductionID: pre.whs_documentation | 1 | item | $1,450 | $1,450 |
| 1. PRELIMINARIES | Site Container, Tool Shed & OfficeID: pre.site_office | 1 | item | $4,500 | $4,500 |
| 1. PRELIMINARIES | Temporary Water & Backflow PreventionID: pre.temp_water | 1 | item | $950 | $950 |
| 1. PRELIMINARIES | Crossover & Kerb ProtectionID: pre.crossover_protection | 1 | item | $1,800 | $1,800 |
| 1. PRELIMINARIES | Site Access Road — Crushed RockID: pre.access_road | 1 | item | $4,800 | $4,800 |
| 1. PRELIMINARIES | Domestic Building Insurance (Home Warranty)ID: pre.home_warranty | 224 | m2 | $1 | $224 |
| 1. PRELIMINARIES | Building Surveyor InspectionsID: pre.inspection_fees | 1 | item | $2,800 | $2,800 |
| 1. PRELIMINARIES | Handover Documentation & CertificatesID: pre.handover_docs | 1 | item | $1,650 | $1,650 |
| 1. PRELIMINARIES | Protection — Films, Goop & Floor ProtectionID: pre.protection_goop | 224 | m2 | $12 | $2,687 |
| 1. PRELIMINARIES | Temporary Stair ProtectionID: pre.stair_protection | 1 | item | $450 | $450 |
| 3. GROUND WORK & EXCAVATION | Compaction Plant & Proof RollID: gnd.compaction | 1 | item | $2,200 | $2,200 |
| 4. CONCRETING | Curing Compound, Expansion Joints & SealantID: con.curing_joints | 15 | m2 | $12 | $180 |
| 18. HYDRAULICS | Under-Slab Drainage & In-Ground PlumbingID: hyd.ground_plumbing | 15 | m2 | $47 | $705 |
| 8. CARPENTRY | Wet Area Wall Sheeting — Villaboard / CFCID: car.wet_wall_sheeting | 44 | m2 | $68 | $2,992 |
| 8. CARPENTRY | Mid-Floor Acoustic Isolation PadsID: car.acoustic_pads | 41 | lm | $18 | $738 |
| 12. DOORS | Entry Door, Frame, Reveals & Sub-SillID: dor.entry_door | 1 | ea | $2,400 | $2,400 |
| 18. HYDRAULICS | Hot Water Pipe LaggingID: hyd.pipe_lagging | 75 | lm | $22 | $1,650 |
| 18. HYDRAULICS | Garden Hose TapsID: hyd.hose_taps | 2 | ea | $220 | $440 |
| 15. WATERPROOFING | Shower Hobs, Leak Control Angles & Water StopsID: wpf.shower_hob | 3 | ea | $380 | $1,140 |
| 14. FLOOR & WALL FINISHES | Carpet, Underlay & Tack StripsID: fin.carpet | 118 | m2 | $85 | $10,030 |
| 14. FLOOR & WALL FINISHES | Engineered Timber / Hybrid Flooring & UnderlayID: fin.timber_floor | 76 | m2 | $145 | $11,020 |
| 14. FLOOR & WALL FINISHES | Floor Levelling CompoundID: fin.floor_leveller | 194 | m2 | $22 | $4,268 |
| 17. PAINTING | Touch-Up & Defect RectificationID: pnt.touch_up | 1 | item | $850 | $850 |
| 23. FIXTURES & FITTING | FlyscreensID: fix.flyscreens | 16 | ea | $185 | $2,960 |
| 23. FIXTURES & FITTING | Security / Barrier DoorsID: fix.security_door | 1 | ea | $950 | $950 |
| 21. LANDSCAPING | Concrete Paths & Porch SurroundsID: pav.paths | 18 | m2 | $135 | $2,430 |
| 21. LANDSCAPING | Clothesline, Letterbox & House NumbersID: lnd.clothesline_letterbox | 1 | item | $850 | $850 |
Design Options & System Scenarios
Side-by-side cost impact of alternative building systems (cladding, framing, structure) on this exact plan.
Brick Veneer
BASELINEThe Australian default. Bricklaying halts in rain and extreme heat — allow program contingency.
Double Brick (Cavity)
+2.8%Heaviest system. Materially increases footing cost on reactive clay. Common in WA, less so in VIC.
Hebel PowerPanel + Render
-0.8%Roughly 60% lighter than brick — can allow a lighter slab on reactive sites. Installs in 3–5 days vs 2–3 weeks for brick, which shortens scaffold hire and supervision. Render needs recoating every 10–15 years.
EPS Foam Panel + Render
-1.0%Highest thermal performance per panel (R1.95–3.31 vs Hebel PowerPanelXL 75mm at R0.52). Lightest system — biggest footing saving. Check NCC combustibility provisions for the building class before specifying.
Lightweight Cladding (Fibre Cement / Composite)
-0.4%Cheapest per m² but needs repainting every 7–12 years — the lowest capital cost, not the lowest life-cycle cost.
Timber Weatherboard
-0.3%Heritage overlay areas in inner Melbourne frequently mandate this.
Commercial Modifiers & Specifications
SECTION 6Adjust builder's margin, contingency allowances, construction systems, regional location factor, and valuation date escalation. Modifying these values updates the project's baseline and recalculates the Bill of Quantities.
Pricing Modifiers, Systems & Escalation Index
Builder's Margin
Applied as a direct commercial multiplier across trade subtotal before GST. Represents overhead, supervision, site administration, and target profit.
Design & Construction Contingency
Allowance for unknown site conditions, documentation gaps, and unforeseen variations during execution.
Trade Sub-total
$1,182,317
Margin 15%
$177,348
Contingency 7%
$82,762
Total Ex-GST
$1,442,427
Total Inc-GST
$1,586,670
Rate $/m²
$6,442
Basis of Estimate & Qualifications
SECTION 7Basis of Pricing
- Quantities have been derived from the supplied architectural drawings, schedules and project metadata.
- Unit rates reflect current competitive subcontractor market conditions in melbourne-metro under rate library vic-metro/2026-Q3.
- Rates exclude GST unless explicitly noted in the final summary.
- Valuation assumes standard working hours, unobstructed vehicular site access, and standard soil bearing capacity (100 kPa) unless noted otherwise.
Standard Exclusions
- Land acquisition, stamp duty, legal and finance holding costs.
- Authority headworks charges, contributions and special council bonds.
- Treatment or remediation of latent contaminated soil / hazardous materials unless explicitly scheduled.
- Loose furniture, soft furnishings and non-fixed equipment (FF&E).
- Escalation beyond the stated valuation period unless covered by the contingency allowance.
PREPARED BY QUANTITY SURVEYING PRACTICE
Ravcon Estimate
Independent Construction Cost Estimating & Quantity Surveying
Authorised Signatory / Reviewer:
DRAFT QS ESTIMATE — FOR TENDER & BUDGET
Date Stamped: 06/08/2026